Education Center
Construction
Week of
January 13, 2002
![]() |
![]() |
|||
| Tuesday,
January 15 -- Concrete was poured to fill in the space between the wall and the slab. |
The
area under the stage and the ramp from the classroom area to the gym were also poured. |
|||
![]() |
![]() |
|||
| The
kitchen area, vertical portions of the stage area, and the rest of the space along the walls will be poured on Thursday. |
Installation
of plumbing began for the primary restrooms in the classroom area. |
|||
![]() |
![]() |
|||
| Wednesday, January 16 -- Concrete forms are built behind the stage area. The last major concrete pour is tomorrow. |
A large load of construction debris is hauled away from the site. |
|||
![]() |
![]() |
|||
| Thursday, January 17 -- Workers start to pour the concrete for the kitchen area. |
When built, the stage will fill the open space on the left and open into the gym. |
|||
![]() |
![]() |
|||
| The finished kitchen floor | These steps are for the right side of the stage. | |||
![]() |
![]() |
|||
| Friday, January 18 -- Forms were removed from the stage and kitchen areas. Framers were also on site for some preliminary work. |
Next week wood will be installed along the roof line where trusses will be installed and the equipment well will be framed out. |
|||
Updated: 10/30/03 |