Education Center Construction
Week of
January 13, 2002

cjan30.jpg (21358 bytes) cjan31.jpg (28689 bytes)
Tuesday, January 15 -- Concrete was poured
to fill in the space between the wall and the slab.
The area under the stage and the ramp from
the classroom area to the gym were also poured.
cjan32.jpg (23945 bytes) cjan33.jpg (24310 bytes)
The kitchen area, vertical portions of the stage
area, and the rest of the space along the
walls will be poured on Thursday.
Installation of plumbing began for the
primary restrooms in the classroom area.
Wednesday, January 16 -- Concrete forms are
built behind the stage area. The last major
concrete pour is tomorrow.
A large load of construction debris
is hauled away from the site.
Thursday, January 17 -- Workers start to
pour the concrete for the kitchen area.
When built, the stage will fill the open
space on the left and open into the gym.
The finished kitchen floor These steps are for the right side of the stage.
cjan40.jpg (26170 bytes) cjan41.jpg (18526 bytes)
Friday, January 18 -- Forms were removed from
the stage and kitchen areas. Framers were also
on site for some preliminary work.
Next week wood will be installed along the roof
line where trusses will be installed and the
equipment well will be framed out.

Last Week | Next Week