Education Center
Construction
Week of
January 20, 2002
![]() |
![]() |
|||
| Monday,
January 21 -- Prior to the installation of the roof trusses, ... |
these
wooden pieces are installed on top of the supporting beams. |
|||
![]() |
![]() |
|||
| Framing
for the equipment well will begin soon in the area at the back of this photo. These trusses are for supporting the heating and cooling equipment in the this area. |
Don't
forget the CLHSA meeting on Saturday, January 26 at 10:00 a.m. There will be a Ladies' Auxiliary meeting at 9:00 a.m. |
|||
![]() |
![]() |
|||
| Tuesday, January 22 -- Installation of trusses for the equipment well began today. |
Wood supports are installed along the back wall. More trusses for the equipment well will be mounted on top. |
|||
![]() |
![]() |
|||
| Wednesday,
January 23 -- Work continued placing wood atop supporting beams and walls. |
More
progress was made in the installation of the equipment well trusses. |
|||
![]() |
![]() |
|||
| Thursday,
January 24 -- The first framing of interior walls began today. |
These
are partial walls for the classrooms along the back wall of the building. |
|||
![]() |
![]() |
|||
| The
large hole in the science lab area was filled with concrete. |
Steel
framing began in the restroom and mens' locker room area of the gymnasium. |
|||
![]() |
![]() |
|||
| Friday,
January 25 -- Particle board is nailed to trusses, forming the floor of the equipment well. |
Particle
board is added to yesterday's framed walls. |
|||
![]() |
![]() |
|||
| Framing
for the womens' locker room is also in progress. |
On
Tuesday, January 29, the installation of the roof trusses will begin. See
you at the CLHSA meeting at |
|||
Updated: 10/30/03 |