Education Center Construction
Week of
January 20, 2002

cjan42.jpg (27549 bytes) cjan43.jpg (29479 bytes)
Monday, January 21 -- Prior to the
installation of the roof trusses, ...
these wooden pieces are installed
on top of the supporting beams.
cjan44.jpg (30388 bytes) cjan45.jpg (15180 bytes)
Framing for the equipment well will begin soon
in the area at the back of this photo. These
trusses are for supporting the heating and
cooling equipment in the this area.
Don't forget the CLHSA meeting on
Saturday, January 26 at 10:00 a.m. There will
be a Ladies' Auxiliary meeting at 9:00 a.m.
cjan46.jpg (23368 bytes) cjan47.jpg (19189 bytes)
Tuesday, January 22 -- Installation of
trusses for the equipment well began today.
Wood supports are installed along the back wall.
More trusses for the equipment well will be
mounted on top.
cjan48.jpg (21886 bytes) cjan49.jpg (29235 bytes)
Wednesday, January 23 -- Work continued
placing wood atop supporting beams and walls.
More progress was made in the installation
of the equipment well trusses.
cjan50.jpg (33498 bytes) cjan51.jpg (41997 bytes)
Thursday, January 24 -- The first framing
of interior walls began today.
These are partial walls for the classrooms
along the back wall of the building.
cjan52.jpg (18049 bytes) cjan53.jpg (23500 bytes)
The large hole in the science lab area
was filled with concrete.
Steel framing began in the restroom and
mens' locker room area of the gymnasium.
cjan54.jpg (29491 bytes) cjan55.jpg (45966 bytes)
Friday, January 25 -- Particle board is nailed to
trusses, forming the floor of the equipment well.
Particle board is added to
yesterday's framed walls.
cjan56.jpg (18129 bytes) cjan57.jpg (20092 bytes)
Framing for the womens' locker
room is also in progress.
On Tuesday, January 29, the installation
of the roof trusses will begin.

See you at the CLHSA meeting at
10:00 a.m. on Saturday, January 26!