Education Center
Construction
Week of
January 27, 2002
![]() |
![]() |
||||||
| Monday, January 28 -- Framing work continued along the back portion of the building today. |
Overnight rains made the gym floor into a reflecting pool. Installation of roof trusses will begin tomorrowweather permitting. |
||||||
|
|||||||
|
|||||||
![]() |
![]() |
||||||
| Wednesday, January 30 -- Steel roof trusses are delivered. |
Wood is attached to the steel trusses in a staging area in the parking lot. The finished trusses will be installed beginning tomorrow. |
||||||
![]() |
![]() |
||||||
| Plumbing in the locker rooms is progressing. Here work on the showers nears completion. |
Framing work continued along the back portion of the building. |
||||||
![]() |
![]() |
||||||
| Thursday, January 31 -- HVAC duct materials began appearing around the site today. |
Framing work around the equipment well continued. |
||||||
![]() |
![]() |
||||||
| Numerous loads of material were hoisted into the equipment well today. |
Plywood flooring was installed along the back portion of the building. The 54-foot trusses will begin bridging this opening next week. |
||||||
![]() |
![]() |
||||||
| Friday, February 1 -- This 90 foot truss will span the length of the gym. |
Trusses were moved into position for easy placement next week. |
||||||
![]() |
![]() |
||||||
| The equipment well will house heating and cooling equipment. This portion of the building will not be covered by the roof. |
Another area of the equipment well. This area is open to the air as well. |
||||||