Education Center
Construction
Week of
February 3, 2002
![]() |
![]() |
|||
| Monday, February 4 -- The recessed entrance on the right side of the chapel was framed out. |
Roof work began today. Workers nail supporting cross members onto the truss. |
|||
![]() |
![]() |
|||
| Particle board is nailed onto the truss and supports, ... |
... the entire assembly is lifted into position, ... | |||
![]() |
![]() |
|||
| ... where it is nailed and welded into place. | Most of the classroom area was enclosed today. By week's end, the majority of the building should be enclosed. |
|||
![]() |
![]() |
|||
| Tuesday, February 5 -- More work took place on the roof today. |
The space above the office area began to be enclosed. |
|||
![]() |
![]() |
|||
| The chapel area was mostly enclosed. | Praise to God for continued progress! | |||
![]() |
![]() |
|||
| Wednesday, February 6 -- Framing began today for the equipment well in the locker room area. It will house the heating and cooling equipment for the restrooms and locker rooms in this part of the building. |
Work on the roof is progressing ahead of schedule. The office, chapel, and classroom areas are nearing completion. |
|||
![]() |
![]() |
|||
| Thursday, February 7 -- Looking from the office area at the front of the building towards the back classrooms |
Roof work by the stage area | |||
![]() |
![]() |
|||
| This wall separates the science lab from the computer lab. |
The recessed entry by the front office is framed. A large crane will be on campus tomorrow to place the large trusses for the gymnasium. |
|||
![]() |
![]() |
|||
| Friday,
February 8 -- The building's largest truss, which spans the gymnasium, was placed early in the day. |
The
trusses and roof panels for the locker room area were placed. |
|||
![]() |
![]() |
|||
| A look from the inside of the locker room area. | Some
interior walls were constructed today as well. By next week Friday, the initial roof work should be completed. |
|||
Updated: 10/30/03 |