Education Center
Construction
Week of
February 10, 2002
![]() |
![]() |
||||||
| Monday,
February 11 -- The locker room area was completely enclosed today. |
Workers
prepare a trusses to be craned into the kitchen/cafeteria area tomorrow. |
||||||
![]() |
![]() |
||||||
| Tuesday,
February 12 -- Trusses were craned into the kitchen/cafeteria area today. |
Here workers weld the trusses into position. | ||||||
![]() |
![]() |
||||||
| Work also began on the gymnasium roof. | Here
workers begin work on the installation of the fire sprinkler system |
||||||
![]() |
![]() |
||||||
| Wednesday,
February 13 -- Work continues on fire sprinklers |
Boundaries
for the back wall and tiers in the chapel are marked on the floor. |
||||||
![]() |
![]() |
||||||
| The
roof over the kitchen and cafeteria is nearly complete. |
Work progresses on the gymnasium roof. | ||||||
![]() |
![]() |
||||||
| More framing in the locker room area. | Workers
dig holes for footings of the awning over the east entrance to the gymnasium. The dark squares on the wall are the attachment points for the awning. |
||||||
![]() |
![]() |
||||||
| Thursday,
February 14 -- Insulation is placed on some of the duct-work in the classroom area. |
With
initial roof work nearing completion, this full-length view will soon be blocked by interior walls. |
||||||
![]() |
![]() |
||||||
| The
last panels of the gymnasium roof were placed today. |
The few remaining openings will soon be closed. | ||||||
![]() |
|||||||
|
|||||||