Education Center
Construction
Week of
March 3, 2002
![]() |
![]() |
|||
| Monday, March 4 -- Rain gutters are installed along the locker room area roof. |
Framing work should be completed this week. Electrical and data boxes need to be placed before drywall installation can begin. |
|||
![]() |
![]() |
|||
| More work on the stage--note the stairs on the left side of the photo. |
Most of the mezzanine flooring is installed. | |||
![]() |
![]() |
|||
| Tuesday, March 5 -- This crane spent most of the day hoisting steel roofing material onto the roof. |
Seen from the equipment well, the newly papered roof is ready for the outer layer of steel to be applied. |
|||
![]() |
![]() |
|||
| Inside framing, electrical, ventilation, sprinkler, and plumbing work continued. This disorienting forest of steel will soon transform into hallways and rooms as insulation and drywall are installed next week. |
While news of funding for the construction continues to be very positive, there is an increasing shortfall in our general operating funds. Please keep the day-to-day needs of CLHS in your prayers and before your congregations. We thank God each day for the love you show to our ministry! |
|||
![]() |
![]() |
|||
| Wednesday, March 6 -- Work begins on the supports for the awnings by the gym entrances. |
The stairs to the mezzanine area in the gym were finished today. |
|||
![]() |
![]() |
|||
| Thursday, March 7 -- A view of the gym from the mezzanine area. |
Rain seeped into the building through unfinished areas of the roof. |
|||
![]() |
![]() |
|||
| Friday, March 9 -- A view across the newly framed cafeteriathe entrance is just right of center in the photo. |
A pallet of drywall sheets is delivered. Insulation and drywall work should begin next week. |
|||
![]() |
![]() |
|||
| A beam of light shines through a hole in the roof. Framing work on the stage area is seen in the background. |
Sink vents for lab station sinks were installed in the science lab. |
|||
![]() |
![]() |
|||
| Support poles for gym entrance awnings were set in concrete today. |
Look for the Crossing the Finish Line video in your congregations over the next few weeks. Only 175 days until the dedication service! |
|||
Updated: 10/30/03 |