Education Center
Construction
Week of
March 10, 2002
![]() |
![]() |
|||
| Monday,
March 11 -- Drywall is hung along the administration area (left) making the hallway actually look like one. |
The
blue steel roofing is being installed adding color to the all white building. |
|||
![]() |
![]() |
|||
| Tuesday, March 12 -- Drywall workers begin taping seams in the administration area. |
Installation of acoustical insulation begins this is the area under the mezzanine. |
|||
![]() |
![]() |
|||
| CLHS alum Jesse Wenzel, of Elgin Electric, installs conduit for data and phone lines. |
A great deal of the roof remains to be covered. | |||
![]() |
![]() |
|||
| Wednesday, March 13 -- Insulation work begins on the gym roof. |
Drywall work in the stage area | |||
![]() |
![]() |
|||
| Thursday, March 14 -- Large ventilation ducts await installation in the gymnasium. |
The stage from across the gymyou can see drywall work in the upper portion of the stage. |
|||
![]() |
![]() |
|||
| Drywall is moved to each room for installation early next week. |
The view from the cafeteria windows | |||
![]() |
![]() |
|||
| Friday,
March 15 -- A large ventilation duct is positioned high above the stage its eventual destination is the gymnasium. |
More insulation work on the gymnasium roof. Next week: Drywall, drywall, drywall |
|||