Education Center Construction
Week of
March 17, 2002

c2mar33.jpg (32652 bytes) c2mar34.jpg (23586 bytes)
Monday, March 18 -- Large ventilation ducts
run into the cafeteria and branch towards
the chapel on the left of the photo.
The smell of tar fills the air as roofers
work on the equipment well.
Tuesday, March 19 -- Today roofers tackled
the equipment well over the locker rooms.
Trusses for the awnings over the gym
entrances were welded into position.
Although this scene seems quiet, it was a
very busy day inside as electricians and
plumbers finished work in walls. Tomorrow
drywall work begins in earnest.
c2mar37.jpg (29221 bytes) c2mar38.jpg (26633 bytes)
Wednesday, March 20 -- Workers hang
drywall in the administration area. They will
Door frames are appearing in the
doorways ahead of the drywall workers.
c2mar39.jpg (27917 bytes) c2mar40.jpg (21047 bytes)
Sheet metal workers pose for a photo on
their way to
lunch. They have been working
on the
equipment well roof.
Work on the steel roof is making
progress towards completion.
Thursday, March 21 -- Steel trusses for awnings
and roof overhangs are painted "C-Hawk blue"
The administration area has drywall and
insulation in place. After inspections the
open side will be drywalled as well.
c2mar43.jpg (23539 bytes) c2mar44.jpg (15387 bytes)
Friday, March 22 -- Drywall and electrical
work progressed in the locker room area.
Next week drywall work will continue. The dry
winter and steady progress have kept the
construction on schedule. At the present time,
we are even a bit ahead of schedule.