Education Center Construction
Week of
March 24, 2002

Monday, March 25 -- Drywall work today was
concentrated in the locker rooms. This wall is
for the sinks in the girls' locker room. The spots
on the photo are drywall dust, which seems
to be particularly fond of camera lenses.
Several loads of steel roofing
material were craned onto the roof. 
c2mar47.jpg (22306 bytes) c2mar48.jpg (35460 bytes)
Tuesday, March 26 -- Drywall work
in the office reception area
The insulation work on the
gym roof nears completion.
c2mar49.jpg (29344 bytes) c2mar50.jpg (20921 bytes)
Awning coverings are installed. Work on the roof continues to progress. Air
conditioning units will be delivered on Friday.
Wednesday, March 27 -- A look across the gym Because of Holy Week and no school next
week, photos of the construction process
will be posted less regularly than usual. 

CLHS Education Center
March 27, 2002

Last Week | Next Week