| Monday, March 25 -- Drywall work today was concentrated in the locker rooms. This wall is for the sinks in the girls' locker room. The spots on the photo are drywall dust, which seems to be particularly fond of camera lenses. |
Several loads of steel roofing material were craned onto the roof. |
||||||
![]() |
![]() |
||||||
| Tuesday,
March 26 -- Drywall work in the office reception area |
The
insulation work on the gym roof nears completion. |
||||||
![]() |
![]() |
||||||
| Awning coverings are installed. | Work
on the roof continues to progress. Air conditioning units will be delivered on Friday. |
||||||
![]() |
![]() |
||||||
| Wednesday, March 27 -- A look across the gym | Because
of Holy Week and no school next week, photos of the construction process will be posted less regularly than usual. |
||||||
![]() |
|||||||
|
|||||||