Education Center
Construction
Week of
March 31, 2002
![]() |
![]() |
||||||
| Monday,
April 1 -- A great deal of drywall work has occurred since last Wednesday. Here we see the office reception area with taping completed. |
The
hallways have almost all of the drywall in place. The classrooms are nearly finished as well. Lack of light in many areas makes photography difficult. |
||||||
![]() |
![]() |
||||||
| Thursday,
April 4 -- Last Friday, HVAC units were craned into position. |
These
larger units are for the chapel and gymnasium. |
||||||
![]() |
![]() |
||||||
| Electricians
spent the day pulling wire from exterior access panels ... |
... to breaker panels inside the building. | ||||||
![]() |
![]() |
||||||
| The main
entry hall is drywalled, taped and ready for texturing. |
The
women's locker room is ready for texturing and tile work. |
||||||
![]() |
|||||||
![]() |
|||||||
| Saturday,
April 6 -- The administration area is texturized. |
|||||||
| Drywall
workers use stilts to get up where the taping needs to be done. |
|||||||
![]() |
|||||||
|
|||||||