Education Center Construction
Week of
April 7, 2002

Monday, April 8 -- Drywall is hung
high above the science lab.
Paint crews texturize walls in the classrooms.
The flash picked up many airborne particles.
It didn't look this messy in actuality!

Tuesday, April 9 -- Looking down the
newly texturized back hallway
towards the gym entrance.

Almost all of the classroom walls have been
texturized. This is the computer lab.
The gym ceiling insulation work was
completed last week. Emergency lighting
fixtures are being installed.
Work on the roof continues
steadily towards completion.
Wednesday, April 10 -- Exterior lights
are being installed around the building.
The front vestibule areas of the
chapel received drywall today.
c2apr20.jpg (19106 bytes) c2apr21.jpg (22889 bytes)
Thursday, April 11 -- Phone and data lines
are pulled to the administration and science
lab areas.
Drywall on the stage is nearly complete.
Emergency lighting fixtures can be seen
in the gym as well.
c2apr22.jpg (41154 bytes) c2apr23.jpg (26204 bytes)
Crews trenched from the road along the back
side of the building to install this flexible
—and earthquake resistant—gas line.
The new gas line is promptly buried.
c2apr24.jpg (30017 bytes) c2apr25.jpg (21110 bytes)
Friday, April 12 -- This is where the gas
service enters the building.
These new electrical boxes appeared
sometime during the past week.
c2apr26.jpg (24426 bytes)

California Lutheran High School
Education Center Construction
April 12, 2002

Last Week | Next Week