Education Center Construction
Week of
April 14, 2002

c2apr27.jpg (16819 bytes) c2apr28.jpg (26700 bytes)
Monday, April 15 -- Data (blue) and fire system
(red) cable continues to be pulled this week
Taping and insulation work around the stage.
The rectangular cut out areas are for
return air flow from the gym.
c2apr29.jpg (20865 bytes) c2apr30.jpg (19602 bytes)
The chapel area is opening up again.
Evidence of ventilation work is seen above.
All the drywall work is making for
some large scrap piles out front.
c2apr31.jpg (13896 bytes) c2apr32.jpg (24277 bytes)
Wednesday, April 17 -- The smell of fresh
paint was everywhere as numerous halls
and classrooms were painted.
Stage lighting and many of the main
lights for the gymnasium were installed.
c2apr33.jpg (10914 bytes) c2apr34.jpg (14561 bytes)
Thursday, April 18 -- Lots of painting took place
today. This is one of the rest rooms in the gym.
The unpainted portion will be covered with tile.
Here one of the back classrooms is
painted in two-tone yellow and blue.

c2apr35.jpg (27138 bytes)

Friday, April 19 -- Electrical, cabling, drywall, roofing, taping
and painting all continued this week. Next week will bring
installation of windows and placement of T-bar for the ceilings.

Last Week | Next Week