Education Center Construction
Week of
April 21, 2002

c2apr36.jpg (26334 bytes) c2apr37.jpg (13904 bytes)
Monday, April 22 -- T-bar for ceilings
is installed in the office reception area.
Two-tone classrooms have been repainted in a
softer off-white color. This is the computer lab.
c2apr38.jpg (18014 bytes) c2apr39.jpg (30491 bytes)
The mezzanine area has been drywalled. All main lighting for the gym has been installed.
Tuesday, April 23 -- T-bar is now
installed in the entire administration area.
Classroom areas are next on the list for T-bar.
Here is work in progress on the science lab.
The only unpainted classroom is located directly
behind the stage. Detail drywall work on five
large closets for gown and drama storage
is nearly complete.
Insulation was placed in the kitchen and
cafeteria today. Drywall should follow
tomorrow. Installation of windows has also
begun. The six large gym windows will be
installed on Wednesday.
c2apr44.jpg (16963 bytes) c2apr45.jpg (15731 bytes)
Thursday, April 25 -- Frames are being installed
in the windows. These are in the cafeteria.
Light fixtures are being installed in the
administration and classroom areas.