Education Center Construction
Week of
April 28, 2002

Tuesday, April 30 -- Workers have been
installing steel sheeting on the undersides
of roof overhangs.
Hallways are becoming less cluttered as
drywall work and painting is winding down.
Drywall work is concentrated in the
kitchen and cafeteria areas this week.
Here is the same area later in the day.
Almost all window frames are
installed and ready for glass.
Power on campus was turned off after
school while electricians energize the
switching gear for the new building.
Thursday, May 2 -- T-bar is installed in all
classrooms. Hallways should be completed
this week.
The classroom behind the stage has now
been painted. Wiring for all ceiling lighting
will begin soon.

Last Week| Next Week