Education Center
Construction
Week of
May 12, 2002
![]() |
![]() |
||||||
| Tuesday,
May 14 -- Glass was installed in many of the windows today. |
Work in the kitchen/cafeteria area continued. | ||||||
![]() |
![]() |
||||||
| Handrails were installed in the stage area. | Vestibule areas are ready for stucco. | ||||||
![]() |
![]() |
||||||
| Wednesday,
May 15 -- Handrails were installed in the access ramp between the gym and cafeteria area. |
Vestibule areas were stuccoed. | ||||||
![]() |
![]() |
||||||
| Tile work begins in the gym restrooms. | Work
began for installing the exhaust hood in the kitchen. |
||||||
![]() |
![]() |
||||||
| Thursday,
May 16 -- Tile work continues by the gym restrooms. |
Installation
of the exhaust hood is completed in the kitchen. |
||||||
![]() |
![]() |
||||||
| With all classroom and hall lights connected ... | ...
cleanup of construction debris has begun. This is the science lab. |
||||||
![]() |
![]() |
||||||
| Friday,
May 17 -- What's missing from this photo? ... The construction office has been moved into the administration area. |
Tile
work in the restroom area of the women's locker room. |
||||||
![]() |
|||||||
|
|||||||