Education Center
Construction
Week of
May 19, 2002
![]() |
![]() |
|||
| Tuesday, May 21 -- A committee meets in the chapel area to select flooring. |
Installation of floor tile is beginning in the restrooms. |
|||
![]() |
![]() |
|||
| Several CLHS seniors have been hired to clean up construction debris. |
Lots of work in the kitchen today. Here the stainless steel serving counter is installed. Storage racks can be seen in the background. |
|||
![]() |
![]() |
|||
| The refrigerator and freezer are now in position. |
A convection oven, griddle, and stove are in position under the exhaust hood. |
|||
![]() |
![]() |
|||
| Thursday, May 23 -- Signs of the Last Days | Main ductwork in the gymnasium is completed. |
|||
![]() |
![]() |
|||
| T-bar is installed in the chapel. | More additions to the kitchenthe dishwasher. |
|||
![]() |
![]() |
|||
| Friday,
May 24 -- Light switches and thermostats were installed today. |
Glass
was installed in the gymnasium entrances. Next week preliminary landscape work begins. |
|||