Education Center Construction
Week of
May 19, 2002

Tuesday, May 21 -- A committee meets
in the chapel area to select flooring.
Installation of floor tile is
beginning in the restrooms.
Several CLHS seniors have been hired
to clean up construction debris.
Lots of work in the kitchen today. Here the
stainless steel serving counter is installed.
Storage racks can be seen in the background.
The refrigerator and freezer
are now in position.
A convection oven, griddle, and stove
are in position under the exhaust hood.
Thursday, May 23 -- Signs of the Last Days Main ductwork in the
gymnasium is completed.
T-bar is installed in the chapel. More additions to the
kitchen—the dishwasher.
c2may44.jpg (8869 bytes) c2may45.jpg (18896 bytes)
Friday, May 24 -- Light switches and
thermostats were installed today.
Glass was installed in the gymnasium entrances.
Next week preliminary landscape work begins.