Education Center Construction
Week of
June 9, 2002

c2jun17.jpg (18182 bytes) c2jun18.jpg (20334 bytes)
Saturday, June 10 -- Cabinets for the
science lab were delivered on Wednesday.
Work began on the basketball supports.
c2jun19.jpg (13239 bytes) c2jun20.jpg (9311 bytes)
Tile work began on Thursday. About half of the rooms were completed
during the week. Remaining tile work should
be done this week.
c2jun21.jpg (19236 bytes) c2jun22.jpg (26497 bytes)
Rough grading was done in
preparation for landscape work.
Grading along Central Avenue
c2jun23.jpg (24431 bytes) c2jun24.jpg (30284 bytes)
Demolition around the modulars is completed.
Removal of the buildings will begin next week.
Most of the palm around the modulars will be
relocated to the front of the property.