Education Center Construction
Week of
June 16, 2002

c2jun25.jpg (22278 bytes) c2jun26.jpg (27207 bytes)
Monday, June 17 -- Work is progressing
on installation of basketball standards.
Here workers install the superstructure
for one of the main court standards.
c2jun27.jpg (15000 bytes) c2jun28.jpg (22952 bytes)
Tile work continues and should
near completion this week.
The first of the relocated
palms at their new home.
Tuesday, June 18 -- Work begins
on the flood control channel. 
The first of the modulars—the restroom
building—is removed from campus.
Work is progressing on the basketball
standards. Work on the standards should
be completed on Wednesday. Installation
of the wood floor will begin on Thursday.
Work on the floor tile is complete
in the classroom area.
Wednesday, June 19 -- Work on the
basketball standards nears completion.
Installation of counters in
restroom areas begins.
Installation of carpeting began today.
This is Pastor Bork's office.
Work in progress in the reception area.
Installation of carpeting should be
completed tomorrow.
Thursday, June 20 -- Work continues
on the flood control channel.
Room 1A and the locker room
modulars are hauled away.
Sinks and mirrors are in place
in all of the restroom areas.
Hoops anyone? Work on the installation
of the wood floor will begin tomorrow.
Carpeting in the reception area Eyewash and safety shower in the science lab
Friday, June 21 -- Grading was done at the
front of the property for upcoming curb and
gutter work.
The new football scoreboard is
on campus awaiting installation.
Tile and baseboard are in place in the chapel ... ... cafeteria, and all other rooms.
Carpet installation is finished
in the administration areas.
The last modular to be removed will
be hauled away early next week.