Education Center
Construction
Week of
June 23, 2002
![]() |
![]() |
|||
| Monday,
June 24 -- With all the modular buildings removed, a large empty space has been opened up. |
Work
on the gym floor begins. Black rubber cushions are attached to the plywood sheets. The plywood will be placed on the concrete, cushion side down. Another layer of plywood on top of that, followed by the hardwood flooring. |
|||
![]() |
![]() |
|||
| A
pressure regulation pump needs to be installed here for the water supply system. Local water pressure varies too much to meet fire codes. The pump will maintain pressure within the necessary range. |
Surveyors
have placed stakes to mark areas for concrete work as landscape work continues. |
|||
![]() |
![]() |
|||
| Tuesday,
June 25 -- Gym floor work continues. A plastic moisture barrier is placed on the concrete, then the cushioned plywood layer. You can see the second layer of plywood— placed diagonally on top of the first layer— on the left side of the photo. |
Detail
paint work begins on the outside of the building. The white finish coats will clean up the edges of the detail work. |
|||
![]() |
![]() |
|||
| Work
continues on the back of the property to add curb, gutter, and landscaping. |
CLHS
Education Center June 25, 2002 |
|||
![]() |
![]() |
|||
| Wednesday,
June 26 -- Student workers apply wax to the classroom floors. |
Progress
continues on the installation of the gym floor. |
|||
![]() |
![]() |
|||
| Detail
work continues on the front of the Education Center ... |
... and on the back as well. | |||
![]() |
![]() |
|||
| Thursday,
June 27 -- Cabinet installation in progress in the faculty work room. |
With
whiteboards and desks in place, the classrooms look almost ready to go. |
|||
![]() |
![]() |
|||
| The
first of the hardwood layer was installed today. |
Here's a closer look. | |||
![]() |
![]() |
|||
| The
exterior paint work on the Education Center ... |
... moves closer to completion. | |||
![]() |
![]() |
|||
| Cabinet
installation is taking place in the cafeteria as well—note the new salad bar. |
Cabinetry
is now in the science lab. Installation should begin next week. |
|||
![]() |
![]() |
|||
| Friday,
June 28 -- Cabinet installation in the faculty work room nears completion. |
More classrooms look ready to go. | |||
![]() |
![]() |
|||
| The
gym floor hardwood is growing towards the sidelines. |
Exterior paint work is nearly finished. | |||
Updated: 10/30/03 |