Education Center Construction
Week of
June 30, 2002

Monday, July 1 -- Doors are installed
on the storage closets in the classroom
behind the stage.
Cabinet installation is complete in the cafeteria.
Steady progress on the gym floor. With the final paint on the outside
of the building, the focus of our ministry
stands out even more.
Tuesday, July 2 -- These 1 1/2 ” boards
are nailed about every 9”. That's a lot of nails!
Work continues in preparation for
landscape at the front of the property.
Wednesday, July, 3 -- A few more days of work should see the rest of the hardwood installed. Final installation of a pressure regulator pump for
the building took place today. It will keep water
pressure to the building at a near constant 70 psi.
Friday, July 5 -- The hardwood
is almost all in place.
Landscape work should bring some
significant changes for next week.