Education Center Construction
Week of
July 7, 2002

Tuesday, July 9 -- Trenching and
installation of irrigation lines took place today.
Water (copper) and gas (black) lines are
mounted on the walls in the science lab.
Wednesday, July 10 -- Irrigation trenches are
filled. Pipe stubbed out at the surface will
provide water for planters and drip line at the
front of the Education Center.
Forms for curb and gutter are constructed
along Central Ave. Similar forms are in place at
the back of the property. Pouring of concrete
will take place on Thursday.
Installation of hardwood flooring
on the stage has begun.
The remaining few feet of hardwood
should be installed today—completing the
most tedious and time-consuming process
of the gym floor project.
Thursday, July 11 -- The hardwood
installation is complete! Next Tuesday,
sanding of the floor will begin.
Hardwood coverings for the stage stairs are
installed. Work continues on the stage floor.
Polypropylene acid-waste pipe is
installed for drainage in the science lab.
Forms for the parking lot and planter
curbing await tomorrow's concrete.
Friday, July 12 -- Concrete for all
curbing was poured today.
Saturday, July 13 -- Curbing for the parking
lot extension in front of the Education Center
The new curb at the front of the property
shows the future width of Central Avenue.
CLHS Education Center
July 13, 2002

Due to vacation plans, there will be no new
images until August 1. Those images should
show a completed Education Center!