Education Center
Construction
Week of
July 7, 2002
![]() |
![]() |
|||
| Tuesday,
July 9 -- Trenching and installation of irrigation lines took place today. |
Water
(copper) and gas (black) lines are mounted on the walls in the science lab. |
|||
![]() |
![]() |
|||
| Wednesday,
July 10 -- Irrigation trenches are filled. Pipe stubbed out at the surface will provide water for planters and drip line at the front of the Education Center. |
Forms
for curb and gutter are constructed along Central Ave. Similar forms are in place at the back of the property. Pouring of concrete will take place on Thursday. |
|||
![]() |
![]() |
|||
| Installation
of hardwood flooring on the stage has begun. |
The
remaining few feet of hardwood should be installed today—completing the most tedious and time-consuming process of the gym floor project. |
|||
![]() |
![]() |
|||
| Thursday,
July 11 -- The hardwood installation is complete! Next Tuesday, sanding of the floor will begin. |
Hardwood
coverings for the stage stairs are installed. Work continues on the stage floor. |
|||
![]() |
![]() |
|||
| Polypropylene
acid-waste pipe is installed for drainage in the science lab. |
Forms
for the parking lot and planter curbing await tomorrow's concrete. |
|||
![]() |
![]() |
|||
| Friday,
July 12 -- Concrete for all curbing was poured today. |
Saturday,
July 13 -- Curbing for the parking lot extension in front of the Education Center |
|||
![]() |
![]() |
|||
| The
new curb at the front of the property shows the future width of Central Avenue. |
CLHS
Education Center July 13, 2002 Due to vacation plans, there will be no
new |
|||