Education Center
Construction
Final Details
![]() |
![]() |
|||
| Tuesday,
August 27 -- A multitude of plants were added around the Education Center today. |
Many
of these trees will be planted along Central Avenue. |
|||
![]() |
![]() |
|||
| The
cross and verse for the gymnasium wall were started today. |
The
artists are Roxanne Alvarado and Mary Kleinschmidt of Christ the Vine Lutheran Church in Temecula. |
|||
![]() |
![]() |
|||
| Wednesday,
August 28 -- The transplanted queen palms give a beautiful look to the front of the Education Center. |
Work
continues on the cross and verse. The senior class of 2002 donated the funds for the project as their class gift. |
|||
![]() |
![]() |
|||
| Thursday,
August 29 -- Two ladies who practice what they paint |
Tuesday,
September 3 -- On the first day of classes the remaining unlandscaped areas were sprayed with hydroseed. |
|||
![]() |
![]() |
|||
| Tuesday,
September 10 -- Bleacher installation is completed. |
Friday,
September 27 -- Workers prepare to lay blacktop along Central Avenue. |
|||
![]() |
![]() |
|||
| By
the end of the school day roads at the front and back of the property are completed. The grass is also doing well. |
Friday,
October 4 -- The patio area in front of the cafeteria is blacktopped. |
|||
Updated: 10/30/03 |