Education Center
Construction
Week of
September 9, 2001
![]() |
![]() |
|||
| Tuesday,
September 11 -- Excavation for sewer and water moves to the front of the site. |
Got concrete? | |||
|
|
||||
![]() |
![]() |
|||
| Wednesday,
September 12 -- Soil is compacted around sewer and water pipes in the north-east corner of the Education Center. This is the future girls' locker room area. |
Trenching
for water and sewer at the front of the property. The foreground is the science lab area. The background trenching is the main restroom and kitchen/cafeteria area. |
|||
![]() |
![]() |
|||
| Friday,
September 14 -- Plumbing for the boys' locker room marks the south-east corner of the building site. |
Look for sewer and water work to wind up next week, and the start of form and rebar work in preparation for pouring the slab. |
|||
Updated: 10/30/03 |
||||