Education Center Construction
Week of
September 16, 2001

csep13.jpg (26800 bytes) csep14.jpg (34212 bytes)
Monday, September 17 -- Most of the work
today was filling and compacting the
trenches of the sewer and water lines.
Tuesday, September 18 -- The first signs of
the impending concrete work appeared today.
This corner marks where the classroom portion
of the building meets the lower gymnasium
portion on the front side of the building.
csep15.jpg (24924 bytes) csep16.jpg (20922 bytes)
Wednesday, September 18 -- With compaction
work done around sewer and water lines, the
locations of the footings are marked on the dirt.
In this view from above, we can see where
many of the concrete footings will be poured.
csep17.jpg (27617 bytes) csep18.jpg (31082 bytes)
Thursday, September 19 -- This will be the
footing along the back wall of the building.
Rebar will start being placed on Monday.
csep19.jpg (19327 bytes) god_first.jpg (36099 bytes)
Friday, September 20 -- With footings mostly
dug, we look forward to the start of concrete
work next week.