Education Center Construction
Week of
September 23, 2001

csep20.jpg (20469 bytes) csep21.jpg (21796 bytes)
Monday, September 24 -- Rebar work for the
footings began today. You can see the first
load of rebar near the large tree on the left.
Tuesday, September 25 -- Rebar work continues
csep22.jpg (37096 bytes) csep23.jpg (31538 bytes)
Front wall footings Footings along Central Ave.
csep24.jpg (20685 bytes) csep25.jpg (31373 bytes)
Wednesday, September 26 -- No visible
changes, but alot of rebar work was done.
For example . . .
csep26.jpg (19634 bytes) csep27.jpg (29661 bytes)
Friday, September 28 -- At last!
Cement trucks!
A steady stream of trucks came
to campus all day.
csep28.jpg (27733 bytes) csep29.jpg (22650 bytes)
All footings were poured on Friday Monday, some final grading and
prep work for pouring the pad.

Last Week | Next Week