Education Center
Construction
Week of
September 23, 2001
![]() |
![]() |
|||
| Monday,
September 24 -- Rebar work for the footings began today. You can see the first load of rebar near the large tree on the left. |
Tuesday, September 25 -- Rebar work continues | |||
![]() |
![]() |
|||
| Front wall footings | Footings along Central Ave. | |||
![]() |
![]() |
|||
| Wednesday,
September 26 -- No visible changes, but alot of rebar work was done. |
For example . . . | |||
![]() |
![]() |
|||
| Friday,
September 28 -- At last! Cement trucks! |
A
steady stream of trucks came to campus all day. |
|||
![]() |
![]() |
|||
| All footings were poured on Friday | Monday,
some final grading and prep work for pouring the pad. |
|||
Updated: 10/30/03 |