Education Center
Construction
Week of
September 30, 2001
![]() |
![]() |
|||
| Tuesday, October 2 -- Loads of sand are delivered and forms for the pad are installed |
A
layer of plastic is covered with sand to provide a barrier to moisture. |
|||
![]() |
![]() |
|||
| A
great deal of rebar needs to be placed before concrete is poured on October 10. |
Trenching
is done to tie the new sewer lines into the exixting sewer lines. |
|||
![]() |
![]() |
|||
| Wednesday,
October 3 -- Plastic sheeting and sand continued to be spread today. More work was also done to tie the new building's sewers into the existing sewer lines. |
Thursday,
October 4 -- Workmen placed rebar today. Though difficult to see in this picture, the area in the back of this photo has all the iron in position |
|||
![]() |
![]() |
|||
| This
is one of the footings to support the roof in the classroom area. |
The
raised open area of dirt will be the location of the stage in the gymnasium. |
|||
![]() |
![]() |
|||
| Workmen
wire together the intersections of the rebar. |
By day's end all the rebar is in position. | |||
![]() |
![]() |
|||
| Friday,
October 5 -- Rebar was positioned in the locker room area of the gymnasium. Small concrete blocks are used to raise the rebar off the ground |
Holes
were drilled in the forms and lengths of rebar were inserted. Everything looks good for pouring the pad on Wednesday, October 10. |
|||