Education Center Construction
Week of
October 7, 2001

coct13.jpg (18488 bytes) coct14.jpg (17713 bytes)
Monday, October 8 -- Another day of
setting rebar and completing sewer work
Tuesday, October 9 -- The pad area is
hosed down in preparation for tomorrow's
concrete work
coct15.jpg (21994 bytes) coct16.jpg (25452 bytes)
With sewer work completed, the trenches
are filled ...
...and the area is graded in preparation
for Wednesday's 4800 yds of concrete.
coct17.jpg (19517 bytes) coct18.jpg (21209 bytes)
Wednesday, October 10 -- At first light
the first of 48 loads of concrete arrives.
By 10:30 a.m. the classroom portion is poured.
coct19.jpg (26410 bytes) coct20.jpg (17149 bytes)
Big equipment for a big job Many students wished they could
have taken a turn on one of these!
coct21.jpg (31559 bytes) coct22.jpg (27612 bytes)
The gymnasium floor is poured ... ... and leveled.
coct23.jpg (18208 bytes) coct24.jpg (24052 bytes)
Looking across the science lab area
towards the chapel and office areas.
By day's end all the floors would be poured.
coct25.jpg (24752 bytes) coct26.jpg (19476 bytes)
Thursday, October 11 -- Today the
new concrete was hosed down ...
...and a sealer coat was applied.
coct27.jpg (38182 bytes) coct28.jpg (29737 bytes)
Friday, October 12 -- This is the grease diverter
that was delivered on Wednesday and hooked
up on Thursday. It keeps grease from our
kitchen from entering the sewer system.
Measurements were made and chalk-lines
snapped to mark the positioning for the forms
for the walls that will be constructed next week.

Last Week | Next Week

Updated: 10/30/03