Education Center
Construction
Week of
October 7, 2001
![]() |
![]() |
|||
| Monday,
October 8 -- Another day of setting rebar and completing sewer work |
Tuesday,
October 9 -- The pad area is hosed down in preparation for tomorrow's concrete work |
|||
![]() |
![]() |
|||
| With
sewer work completed, the trenches are filled ... |
...and the area is graded in preparation for Wednesday's 4800 yds of concrete. |
|||
![]() |
![]() |
|||
| Wednesday,
October 10 -- At first light the first of 48 loads of concrete arrives. |
By 10:30 a.m. the classroom portion is poured. | |||
![]() |
![]() |
|||
| Big equipment for a big job | Many
students wished they could have taken a turn on one of these! |
|||
![]() |
![]() |
|||
| The gymnasium floor is poured ... | ... and leveled. | |||
![]() |
![]() |
|||
| Looking
across the science lab area towards the chapel and office areas. |
By day's end all the floors would be poured. | |||
![]() |
![]() |
|||
| Thursday,
October 11 -- Today the new concrete was hosed down ... |
...and a sealer coat was applied. | |||
![]() |
![]() |
|||
| Friday,
October 12 -- This is the grease diverter that was delivered on Wednesday and hooked up on Thursday. It keeps grease from our kitchen from entering the sewer system. |
Measurements
were made and chalk-lines snapped to mark the positioning for the forms for the walls that will be constructed next week. |
|||