Education Center
Construction
Week of
October 14, 2001
![]() |
![]() |
|||
| Tuesday,
October 16 -- Forms for an interior wall were put into position. The curved piece and rectangular elements will add some interest to the concrete wall. |
Seen
from above, the right side of the wall will be tipped up to form the back of the chapel and kitchen areas. |
|||
![]() |
![]() |
|||
| Wednesday,
October 17 -- More forms for walls are constructed. This form shows the curve of the roof. |
A View from Above | |||
![]() |
![]() |
|||
| Thursday,
October 18 -- Construction on the forms for the walls continues. |
Because
of limited space, some walls will be poured some distance from their actual position and will be moved by crane to the proper place. |
|||
![]() |
![]() |
|||
| Friday, October 19 -- Installation of the steel rebar will begin Monday and will take several weeks. | A
great deal of detail work is necessary on the forms. |
|||
Updated: 10/30/03 |