Education Center Construction
Week of
October 14, 2001

coct31.jpg (27488 bytes) coct32.jpg (19130 bytes)
Tuesday, October 16 -- Forms for an interior
wall were put into position. The curved piece
and rectangular elements will add some interest
to the concrete wall.
Seen from above, the right side of the wall
will be tipped up to form the back of the
chapel and kitchen areas.
coct33.jpg (26618 bytes) coct34.jpg (20754 bytes)
Wednesday, October 17 -- More forms for
walls are constructed. This form shows the
curve of the roof.
A View from Above
coct35.jpg (25254 bytes) coct36.jpg (22367 bytes)
Thursday, October 18 -- Construction
on the forms for the walls continues.
Because of limited space, some walls will be
poured some distance from their actual position
and will be moved by crane to the proper place.
coct37.jpg (21773 bytes) coct38.jpg (19547 bytes)
Friday, October 19 -- Installation of the steel rebar will begin Monday and will take several weeks. A great deal of detail work is
necessary on the forms.