Education Center Construction
Week of
October 21, 2001

coct39.jpg (23942 bytes) coct40.jpg (30306 bytes)
Monday, October 22 -- While construction
of forms for the wall continued on the east
side of the site ...
... the completed forms on the west side
were cleaned and a sealer coat was
applied to concrete and forms to prevent
bonding with the poured walls.
coct41.jpg (21782 bytes) coct42.jpg (26553 bytes)
Tuesday, October 23 -- Not many obvious
changes since yesterday. Detail work was
done on the east side forms (foreground)
and sealer was sprayed on the concrete.
This photo shows some of the detail work that
will appear on an outside wall of the building.
Expect for some iron work soon.
coct43.jpg (32936 bytes) coct44.jpg (32630 bytes)
Thursday, October 25 -- Rebar for
the walls is delivered
Placing the rebar in the walls. Pouring of the
first set of walls should be around November 6.
coct45.jpg (26470 bytes) coct46.jpg (31395 bytes)
Friday, October 26 -- More rebar is delivered. The next week and a half will be taken
up by installing rebar in the wall panels

Last Week | Next Week

Updated: 10/30/03