Education Center
Construction
Week of
October 21, 2001
![]() |
![]() |
|||
| Monday,
October 22 -- While construction of forms for the wall continued on the east side of the site ... |
...
the completed forms on the west side were cleaned and a sealer coat was applied to concrete and forms to prevent bonding with the poured walls. |
|||
![]() |
![]() |
|||
| Tuesday,
October 23 -- Not many obvious changes since yesterday. Detail work was done on the east side forms (foreground) and sealer was sprayed on the concrete. |
This
photo shows some of the detail work that will appear on an outside wall of the building. Expect for some iron work soon. |
|||
![]() |
![]() |
|||
| Thursday,
October 25 -- Rebar for the walls is delivered |
Placing
the rebar in the walls. Pouring of the first set of walls should be around November 6. |
|||
![]() |
![]() |
|||
| Friday, October 26 -- More rebar is delivered. | The
next week and a half will be taken up by installing rebar in the wall panels |
|||
Updated: 10/30/03 |