Education Center Construction
Week of
October 28, 2001

coct47.jpg (22966 bytes) coct48.jpg (25780 bytes)
Monday, October 29 -- This week will be
taken up with the installation of rebar
in the forms for the walls.
The next photos posted will be
of Wednesday, October 31.
coct49.jpg (25832 bytes) coct50.jpg (47329 bytes)
Wednesday, October 31 -- A great deal of
rebar was installed over the past few days.
Things are still on track for pouring the
walls the middle of next week.
The walls that will be supporting the roof
are thicker and have a double-layer of rebar.
cnov01.jpg (37069 bytes) cnov02.jpg (34600 bytes)
Friday, November 2 -- Steel connectors are
installed to serve as attachment places
along the roof-line.
Some welding is done to solidify
some rebar connections.
Next Week: 22 of 37 wall panels will be poured

Last Week | Next Week