Education Center
Construction
Week of
October 28, 2001
![]() |
![]() |
|||
| Monday,
October 29 -- This week will be taken up with the installation of rebar in the forms for the walls. |
The
next photos posted will be of Wednesday, October 31. |
|||
![]() |
![]() |
|||
| Wednesday,
October 31 -- A great deal of rebar was installed over the past few days. Things are still on track for pouring the walls the middle of next week. |
The
walls that will be supporting the roof are thicker and have a double-layer of rebar. |
|||
![]() |
![]() |
|||
| Friday,
November 2 -- Steel connectors are installed to serve as attachment places along the roof-line. |
Some
welding is done to solidify some rebar connections. Next Week: 22 of 37 wall panels will be poured |
|||
Updated: 10/30/03 |