Education Center Construction
Week of
November 4, 2001

cnov03.jpg (40298 bytes) cnov04.jpg (39250 bytes)
Tuesday, November 5 -- The white inserts will
allow bracing poles to be attached when the
walls are poured.
Electrical boxes and conduit are installed
into the walls prior to pouring. Pouring of
the walls will take place Monday and
Tuesday of next week.
cnov05.jpg (26077 bytes)

Wednesday, November 6 -- More electrical
and cleanup work is done. Wall panels will
be poured on Monday and Tuesday.