Education Center Construction
Week of
November 11, 2001

cnov06.jpg (21994 bytes) cnov07.jpg (22532 bytes)
Monday, November 12 -- About half of the
twenty-two wall panels that have been
formed were poured today.
Weather permiting, the remainder of the
panels will be poured tomorrow.
cnov08.jpg (27125 bytes) cnov09.jpg (19975 bytes)
The panels need at least ten days to harden fully. They will be hoisted into position
on Monday, November 26.
cnov10.jpg (27799 bytes) cnov11.jpg (31217 bytes)
Tuesday, November 13 -- After some overnight
rains, there was sufficient clearing to allow
the pouring of the remaining wall panels.
All the panels were completed by
around 10:00 a.m.
cnov12.jpg (27022 bytes) cnov13.jpg (21028 bytes)
There will be little construction activity until
the panels are positioned on November 26.
Photos will be posted when something
of interest occurs.
cnov14.jpg (27405 bytes) cnov15.jpg (32735 bytes)
Wednesday, November 14 -- Workmen
remove the forms from around the wall panels.
Soon it will be possible to walk
through this doorway!
cnov16.jpg (34847 bytes) cnov17.jpg (19801 bytes)
Thursday, November 15 -- Bracing poles for
the wall panels are delivered.
Attachment points for the bracing poles
are exposed in the wall panels.