Education Center
Construction
Week of
December 2, 2001
![]() |
![]() |
|||
| Monday,
December 3 -- Soil is removed from the area that will be the stage. This will allow under-stage storage to be built for chair storage. |
The
process of careful measurement begins again to build the forms for the remaining fifteen wall panels. |
|||
![]() |
![]() |
|||
| Tuesday,
December 4 -- Workers grind and sand the rough spots on the exterior walls. |
Another crew follows behind patching and filling. | |||
![]() |
![]() |
|||
| The next set of forms take shape. | The
ironwork for supporting the roof trusses is delivered. |
|||
![]() |
![]() |
|||
| Wednesday, December 5 | More form construction today | |||
![]() |
![]() |
|||
| Thursday,
December 6 -- Workers install a ledger to support the roof trusses over the locker room area. |
A
temporary strip of concrete is poured to make room for the construction of some forms for two of the larger panels. The strip will be removed once the walls are erected. |
|||
![]() |
![]() |
|||
| Installation
of rebar for the next set of forms should begin Monday. |
A look through the office window | |||
![]() |
![]() |
|||
| Friday,
December 7 -- A ledger for the chapel roof trusses is hoisted into position. |
Most
of the work on the forms was completed today. |
|||