Education Center Construction
Week of
December 2, 2001

cdec01.jpg (17908 bytes) cdec02.jpg (19114 bytes)
Monday, December 3 -- Soil is removed from
the area that will be the stage. This will allow
under-stage storage to be built for chair storage.
The process of careful measurement begins
again to build the forms for the remaining
fifteen wall panels.
cdec03.jpg (17755 bytes) cdec04.jpg (19573 bytes)
Tuesday, December 4 -- Workers grind and
sand the rough spots on the exterior walls.
Another crew follows behind patching and filling.
cdec05.jpg (27352 bytes) cdec06.jpg (36374 bytes)
The next set of forms take shape. The ironwork for supporting
the roof trusses is delivered.
cdec07.jpg (22942 bytes) cdec08.jpg (27930 bytes)
Wednesday, December 5 More form construction today
cdec09.jpg (18965 bytes)
Thursday, December 6 -- Workers install a
ledger to support the roof trusses over the
locker room area.
A temporary strip of concrete is poured to
make room for the construction of some
forms for two of the larger panels. The strip
will be removed once the walls are erected.
cdec11.jpg (29394 bytes) cdec12.jpg (22361 bytes)
Installation of rebar for the next set of
forms should begin Monday.
A look through the office window
cdec13.jpg (26202 bytes) cdec14.jpg (30016 bytes)
Friday, December 7 -- A ledger for the
chapel roof trusses is hoisted into position.
Most of the work on the forms
was completed today.