Education Center Construction
Week of
December 9, 2001

cdec15.jpg (33475 bytes) cdec16.jpg (29028 bytes)
Monday, December 10 -- Installation of
rebar begins on the last set of wall panels.
Workers work on the back wall where
phone and data lines will enter the building.
cdec17.jpg (24479 bytes) cdec18.jpg (23986 bytes)
Tuesday, December 11 -- Rebar work
continued today.

In the locker room area, progress was
made on some of the plumbing work.                                                                           

cdec19.jpg (24548 bytes) cdec20.jpg (25646 bytes)
Wednesday, December 12 -- Plumbing
work continues in the locker room area.
Work on rebar continued. The forms are scheduled
to be poured one week from today, December 19.
cdec21.jpg (18097 bytes) cdec22.jpg (26346 bytes)
The chapel walls stand alone--for now. The focal point of the building, and the focal point
of our ministry will be the outside wall of the chapel.
cdec23.jpg (23627 bytes) cdec24.jpg (21366 bytes)
Thursday, December 13
More plumbing progress
The view from the office window. Things are
still on track for pouring the last wall panels
next Wednesday, December 19.