Education Center
Construction
Week of
December 9, 2001
![]() |
![]() |
|||
| Monday,
December 10 -- Installation of rebar begins on the last set of wall panels. |
Workers
work on the back wall where phone and data lines will enter the building. |
|||
![]() |
![]() |
|||
| Tuesday,
December 11 -- Rebar work continued today. |
In the locker room area, progress was |
|||
![]() |
![]() |
|||
| Wednesday,
December 12 -- Plumbing work continues in the locker room area. |
Work
on rebar continued. The forms are scheduled to be poured one week from today, December 19. |
|||
![]() |
![]() |
|||
| The chapel walls stand alone--for now. | The
focal point of the building, and the focal point of our ministry will be the outside wall of the chapel. |
|||
![]() |
![]() |
|||
| Thursday,
December 13 More plumbing progress |
The
view from the office window. Things are still on track for pouring the last wall panels next Wednesday, December 19. |
|||
Updated: 10/30/03 |